The big spill nine years after
Oscar P. Clarke Stabroek News - Georgetown September 2004
Nine years after cyanide-laced effluent spilled into the Essequibo
River from the Omai River following an Omai Gold Mines Ltd (OGML)
tailings pond failure, life in the area has generally resumed its
normal course with residents freely using water from the Essequibo,
once deemed a dangerous exercise.
And as OGML prepares to wrap up its gold-mining operations in that
area by next year, environmentalists, while cognisant of what might
have been, consider that the spill resulted in some good since it
brought such issues to the fore and saw the stiffening of
environmental laws.
Meanwhile, settlement of a lawsuit filed against the company
following the spill on behalf of some 200-odd affected riverain
residents continues. XXX learned that the out-of-court settlement
at an average of $50,000 per person started two years ago.
On Sunday, August 21, 1995 effluent from a ruptured tailings pond
at the giant interior mining facility poured uncontrollably into
the Omai River and subsequently into the Essequibo. It is today
still considered the country's most serious environmental
accident.
However, this was not the first time that cyanide-laced tailings
had managed to find its way into the neighbouring waterways; there
had been a spill a mere three months earlier.
Unlike the magnitude of the August spill, the one in May of the
same year received little mention although murky tailings were
evident in the Omai River. Indeed that minor spill was not reported
to government for six days.
Attempts to obtain a detailed response from OGML proved futile.
When contacted, OGML Communications Officer Sita Mohamed said the
spill's memory was not something the company wished to make a fuss
about.
It was a bleak day for the gold-mining entity. OGML, with its
up-to-date laboratory facilities and monitoring to ensure adherence
to standards, had held itself up as a beacon in the local mining
industry. The 'cyanide spill' as it became known changed all that
and as far as riverain residents were concerned, made the name Omai
synonymous with poison.
In relation to OGML's end-of-operations preparations Mohamed said a
detailed closure plan had been submitted both to the Environmental
Protection Agency (EPA) and the Guyana Geology and Mines Commission
(GGMC). OGML is currently awaiting comments on the document from
the latter.
However, a recent corporate update from Omai's parent company
Cambior Inc said that increase in mineral reserves in the Fennel
pit and production delays during the rainy season will push
production from the pit onto year end; well beyond the planned
August closure.
Current production from the pit is being complemented with
low-grade hard rock ore from stockpile. According to the release
some 3.7 million tonnes at 0.9 g Au/t will remain to be processed
in the first nine months of 2005 for a production of 100,000 ounces
of gold.
Current gold production initially forecast at 234,000 ounces is not
estimated to reach some 240,000 ounces.
Former EPA Director of Environmental Management Unit Dr David Singh
in a recent interview confirmed that such a plan had been furnished
to the EPA.
According to Singh this plan has from time to time been regularly
updated to keep it consistent with changing trends of environmental
safety and other implications.
Shock and horror
At the time of the spill, Singh was employed at the University of
Guyana as a lecturer in the Environmental Studies Unit (ESU). He
had played a critical role in gathering samples and testing the
immediate environment in the aftermath of the disaster.
Singh vividly recalls the early Sunday morning call some time
around 6 am from Presidential Adviser on the Environment, Navin
Chandarpal informing him about an accident at Omai and asking him
to be part of a delegation that would visit the mines that
morning.
"At that time I was unaware of the magnitude of the spill. [It was
not] until [we were] airborne that a little more information was
released," Singh said.
And it was only then that the possibility of cyanide-contaminated
material flowing into the Essequibo River as a result of a breach
had been raised.
Singh remembered that other members of the team aboard the aircraft
that morning included William Woolford from GGMC as well as Hilbert
Shields of the Guyana Gold and Diamond Miners Association
(GGDMA).
The magnitude of the situation was revealed as the aircraft neared
the mining facility. The team's first glimpse of the situation was
reddish, murky water cascading out of the damaged pond into the
Omai River. Singh recalled his shock and horror at seeing the murky
fluid.
However, he noted the company's efforts to channel some of the
tailings water into the Fennel pit as a temporary measure to reduce
some of the spillage from the damaged pond. Fluid in the tailings
pond had been high mainly because of the increased volume of
rainfall in the area, which seemed to have added stress to an
already strained pond. It subsequently broke under pressure.
On the ground, Singh said, the team was better able to survey the
area while being briefed by Omai officials, which allowed a clearer
picture of what exactly occurred.
"Up to this point my knowledge of mining, it effects and the use of
cyanide was fairly academic," Singh said.
He said once apprised of the situation, the team moved to swiftly
establish efforts to monitor it. "This was done at two levels, the
monitoring of the water samples from various points in the river
along with the receipt of hourly reports from the company," Singh
said.
He recalled data being faxed into the University of Guyana's ESU
where it was manually placed onto charts and used as a guide to
plot levels of contamination at various points in the river.
"For two weeks after the spill it was mostly round-the-clock work
for personnel from the unit who apart from engaging in their usual
work during the day undertook to collect and manually map data onto
a spread sheet to determine the trends of the spill and its
consequences," Singh said.
Not all personnel at the university were keen on being involved as
no official directive had been given but a lot of help was received
from the Institute of Applied Science and Technology (IAST) as well
as final-year Environmental Studies students. Many assisted in
collecting samples for testing by the unit.
Singh also recalled the IAST head's responsiveness to requests for
assistance along with his willingness to put the agency's
resources, though lacking, at the disposal of the ESU.
"Omai stepped in and gave us some chemicals and other instruments
to allow us to undertake our own tests," he said. According to
Singh, each of the tests took six hours and was extremely
difficult. Sampling was being done on an hourly basis and the tests
followed a two-step approach each of which took three hours.
So as to better understand the effects of cyanide, particularly on
people in the event they came into contact with the contaminated
water, detailed research was done on its properties and effects.
This was done using the spill as an example and focusing on the
amount of cyanide that would have been contained in the spilled
tailings, rather than raw cyanide.
According to the environmentalist, a week after the spill, a
rigorous sampling campaign was done on the Essequibo River at
various points, starting from the Omai River.
Meanwhile, government had declared the situation an environmental
disaster and harnessed all resources to deal with it. According to
Singh, who joined the staff of Iwokrama last year as acting adviser
on Resource Management and Training, it was this, which showed
government's keenness on stressing the importance of environmental
concerns.
Singh, who was also involved as consultant on the review committee
to oversee Omai's implementation of the necessary corrective
measures noted that cyanide does not stick around as is the case
with other substances used in mining including metal and
mercury.
However long-time advocate Judith David who stridently fought on
behalf of residents of riverain communities all the way to the
courts said some are still feeling the effects of the spill nine
years after it severely affected their livelihood.
According to David the compensation given by Omai was an insult,
bearing in mind the effects of the spill and the fact that
government had declared the area a national disaster.
She alluded to a similar occurrence in Canada in a lake where a
small cyanide spill led to the closure of the water body
permanently.
However within ten days of the spill the Essequibo River was
declared safe of contaminants, David said. This she said occurred
despite clear evidence that there were effects on the food chain
including dead poultry, fish, and wild animals among other
things.
Even today the fish family in the river has never developed the way
it was prior to the spill, David said.
David a resident of Bartica recalled awaking on the day of the
spill to find discoloured water all around. Regional Chairman at
the time Brentnol Archer informed them that there had been a
cyanide spill at Omai and that they needed to refrain from using
the water, she said, and the message was also sent to riverain
communities. According to David people were affected in different
ways and she feels Cambior and Omai never disclosed the truth with
respect to the cyanide spill including the effects of other
particles apart from the deadly poison.
She also demanded to know in the interest of the communities, what
is contained in the Omai closure plan. "The plan needs to be made
public so that we will see what will happen after the mine closes,"
David said. David was also not satisfied with the way the court had
dealt with the Omai matter, which she said is still pending up to
today.
Long term
Singh was of the opinion that the spill resulted in more good than
harm since it facilitated the development of a stringent
environmental mechanism, while nurturing greater focus on like
issues.
He felt that only certain pockets of the population focus on the
environment, which is more of an urban rather than a rural problem
than people make it out to be.
"In one sense the spill woke us up as it was the necessary antidote
that helped in the framing of the Environmental Protection Act and
also the Iwokrama Act both legislated on and passed shortly after
the incident," he said.
Singh saw the spill as the required medicine needed to jump-start
the whole environmental movement, which he sees as still focused
merely on the hinterland and not catching the broader attention of
society.
Singh also does not think that any long-lasting effects are evident
from the spill especially since the cyanide was mixed with other
chemicals making it less reactive.
He felt that any cyanide, if it remained, had either been washed
away with the moving tide into the open seas or settled below heaps
of deposits in sections of the Essequibo River.
Cyanide, from a technical standpoint, is a chemical whose immediate
effects could be catastrophic but once this initial phase is
overcome it is less likely to be lethal.
Closure plan
Omai's submission to the EPA setting out detailed plans for the
area once mining is over also drew some comment from Singh. He
noted its continued revision as more information becomes
available.
Among the details articulated in the plan, is how the property is
to be protected from incursion particularly from small miners
interested in exploring the contents of the tailings pond.
The plan also features continued monitoring of cyanide levels in
the ponds as they depreciate to acceptable levels to facilitate
discharge into the nearby waterways.
However Singh's main concern is about OGML walking away without
leaving money in escrow to enable government to take care of the
environment at the mining facility.
And he sees it as sad if the property is allowed to be engulfed by
the surrounding jungle instead of being used as a training ground
for young people, a plan articulated by Major General (rtd) Joseph
Singh.
"It could also be used as a tour site to which visitors interested
in seeing what a mine location looks like can go," Singh
said.
Singh was also concerned about the upkeep of the Linden/Mabura Road
link with the impending winding down of OGML's operations. The
mainly laterite surface has been maintained by the mining firm as a
means of accessing its mine site.
However, once operations have wound up there would no longer be a
need for OGML to continue to shell out money to maintain the
road.
Government's focus
But there were varied accounts of the events that led to
government's declaration of the spill as a national disaster.
According to a normally reliable source, the spill initially
appeared to be of little importance. However, once its magnitude
became evident, there was a knee-jerk reaction, with officials
scrambling to respond in an ad-hoc fashion.
Several years ago the EPA had termed efforts by OGML to improve its
environmental management as steady. One of the main matters coming
out of the cyanide waste spill was the construction of a new
tailings pond. Then operations director of the EPA, Denise Fraser,
had told this newspaper that based on the experience of the old
tailings pond, careful examination had to be done of the new
design.
An Environmental Impact Assessment was done for the new dam and was
approved by the EPA.
A discharge criterion for the effluent was set and a contingency
plan, which lays out the risks involved and the responses in the
event of any incident, had to be established by the company.
The EPA is responsible for overseeing regular soil and water
sampling including other forms of testing. Results of EPA tests are
normally compared to those of OGML to check for disparities and to
determine whether they comply with the strict criteria set by the
monitoring agency.
OGML, XXX understands, does day-to-day monitoring and is in regular
contact with the EPA, for which it prepares a monthly report. Every
two months, meetings comprising representatives of the GGMC, OGML
and the EPA are held to review the company's activities.
The EPA and GGMC had signed a Memorandum of Understanding (MOU),
which set out how the two agencies would work together on
environmental matters.
Surveys of the aquatic life in the area affected by the spill done
by University of Guyana scientists in 1998 had concluded that life
had returned to normal. "There were no long-lasting effects. There
now are mechanisms in place to prevent another spill. These
mechanisms are systematically being built up. The likelihood of a
recurrence is very small," former EPA Director Per Bertilsson had
said.
Some new stipulations installed after the spill included an
environmental monitoring plan and a contingency plan for the larger
operations. One beneficial aspect of the whole incident was that
Guyanese professionals were involved in the decision-making
process, Dr Singh had told XXX
Previously, leading up to the investment, OGML had autonomy in this
process and the local technical people were not called upon for
their contributions.
"Prior to the incident, information just filtered down to us. We
were not allowed any technical input. The spill provided a
watershed for a large number of environmental issues to come to the
fore," Dr Singh had said.
The spill led to the establishment of the Environmental Protection
Act, which was immediately placed on the front burner and was
enacted the following year.
After the spill, Omai volunteered US$100,000 in equipment to
refurbish the Environmental Testing Laboratory at IAST.
The number two tailings pond was a part of the terms of resumption
agreed between OGML and the government.
Lawsuits
Hundreds of lawsuits were filed against OGML after the spill. The
majority of the court proceedings were filed by persons living in
the areas affected by the slurry, which wended its way down the
Essequibo River.
Attorney-at-law Moses Bhagwan had lodged over 200 claims against
the company on behalf of clients. He began to institute legal
proceedings against OGML not long after the spill. Claims consisted
of those filed by loggers, hunters, farmers, traders, miners, and
fishermen.
Bhagwan had said for the period the area had been declared a
disaster zone, many persons lost income because they could not have
carried on normal economic activities. "Life for many has never
been the same," the lawyer had said.
Discussions were initiated with lawyers representing the insurers
of the company, Bhagwan said, and a process to deal with all the
claims was agreed upon. He revealed that the parties involved were
close to a full settlement following a meeting in Miami three years
ago. However, this fell through when a class-action suit was filed
around the same time by Recherches Internationales Quebec in
Canada.
The group had filed on behalf of 23,000 persons. A court in Canada
subsequently declined jurisdiction.
"Since the negotiation mechanism was disrupted, the process
[became] tedious, painful and generally unproductive," Bhagwan
said.
However, settlement was finally reached and the process of paying
the 200-odd respondents who Bhagwan represented, his secretary
said, was ongoing.
Meanwhile, members of the Independent Commission of Inquiry
established to lobby on behalf of residents in affected riverain
communities through their new chairman, a US-based attorney, are
seeking to reopen the Omai cyanide spill case in Canada.
To this end, a signature campaign has been launched at Bartica and
within riverain communities, correspondence from the commission
recently said.
However in the correspondence the commission's Secretary Mohamed
Kalamadeen alluded to OGML's satisfactory dealings with residents
in the affected communities. "Residents can raise their head and
say that Omai had indeed honoured their promises and commitments,"
Kalamadeen said.
He also congratulated Omai on its achievement of being the first
South American mining company to attain the ISO-1400 Standard
pointing out that achieving that level of certification is not
easy.
He said Omai has been working along with various riverain
communities while constructing health centres at Fort Island,
Rockstone, Agatash with another being built in the middle
Mazaruni.
This apart, the company has always responded positively to requests
for medical outreach visits to several riverain communities. It has
also responded positively to education by contributing to the
facilitation of the Bartica Secondary School computer lab among
other things.
A recent release from Omai alluded to the soon to be completed
health and community centre at Aliki. They have also assisted the
Rockstone community by enclosing the incomplete headmistress
building to house two teachers in the area.
No reason for hype
Today OGML is adamant that there is no long-term effect. Life has
returned to normal, it says, and there is no reason for the hype,
which surrounded the spill.
"The impact of the spill was not what was originally thought,"
OGML's Human Resources Manager, Norman McLean had told Stabroek
News some time ago.
McLean said the people got "carried away" over the discolouration
of the Essequibo River during the spill. But this was as a result
of the saprolite used in the construction of the tailings dam,
which was also washed away.
The reddish-brown colour, which overpowered the Omai River and part
of the Essequibo, is associated with the use of cyanide. This was
what had everyone concerned over the perceived level of the poison
in the waterways. The company said the cyanide concentration in the
Essequibo River was way below the level for drinking water
standards.
Mechanisms were put in place before the company resumed operations
on February 4, 1996, to prevent any recurrence of a spill. The
effluent treatment plant and the holding pond were originally in
the company's plans before the spill but were installed afterwards.
A new spigotting method was also adopted and the design of the
tailings pond changed.
Omai also had an environmental programme in place before the spill.
This was one of the requirements of the lending institutions before
credit is approved.
"Once you're gonna borrow money from the banks internationally you
have to come up with an environmental impact statement and you have
to have a programme for the environment," McLean had
asserted.
Three committees were set up to conduct studies on the impact of
the spill. They were the process review committee, tailings dam
committee and the environment audit committee.
The first committee examined the process used by the company to
extract gold and the feasibility of alternative methods but
concluded that the use of cyanide was the best and least
costly.
"The committee established quite clearly that there was no other
process which is better than the use of cyanide [in extracting
gold]," McLean said.
Ninety-five per cent of the gold produced in the world is done so
by the use of cyanide. The other five per cent is produced by
mercury, XXX understands. Mercury, unlike cyanide, is not
biodegradable and it was found that the latter is safer and more
economical to use.
There were several features added to the new tailings pond. The
company employed a new technique called spigotting. Using this
method, all the waste material coming from the mill enters the dam
via a pipe, which empties the gravel and cyanide-laced water into a
perforated pipe that is installed in the tailings pond.
This pipe is movable and is positioned in various areas around the
pond so that the solution coming out of the mill is distributed in
an even manner throughout the pond. The result leaves the dam with
a beach-like effect.
The new dam is three times the size of the failed tailings dam. It
is built entirely with compacted saprolite unlike the former one
which had three tiers comprising of, first, a rip-rap design, then
a filter followed by the saprolite.
The government has approved the discharge of effluent into the
holding pond at 700 gallons per minute. The effluent from the
tailings dam is channelled to the holding pond where it is tested
to determine the cyanide concentration before being discharged in
the Essequibo River.
McLean had noted that the Omai location experienced heavy
precipitation, which causes a build-up of water in the tailings
pond, hence the approved rate of discharge. However, the company
discharges at a rate of 400 gallons per minute. Unlike any other
gold mine in the world OGML has to satisfy the discharge criteria
as established in the United States, Guyana and Canada
collectively.
For Canada, there is an end of pipe criterion. This means that the
material coming out of the gold mill should not contain more than
1.5 parts per million (ppm) of cyanide.
In the US there is the receiving water criterion where the effluent
discharged into waterways has to be done ensuring that the area 100
metres below the discharge point is not more than 5.2 parts per
billion of cyanide.
In Guyana's case, the government has implemented a loading factor
of not more than 25 kilogrammes of cyanide per day to be discharged
into the waterways. From the holding pond, the effluent is
discharged into the Essequibo River through a diffuser. The
diffuser is 200 metres long and the effluent is pumped through 200
port holes in the diffuser pipe.
The effluent treatment plant was constructed at a cost of some US$3
million to treat waste before its discharge into the Essequibo
River. In the plant, hydrogen peroxide, ferric sulphate and caustic
soda are used to break down cyanide.
Because of the effect of sunlight on the mill waste in the tailings
pond, natural degradation of the cyanide occurs. If for any reason
the material from the mill is more than the 1.5 ppm limit, it would
be channelled to the effluent treatment plant to be broken down
before being discharged.
Ferric sulphate is used in the effluent treatment plant to clear up
the solution, which McLean boasted is coming out of the plant like
purified water.
The EPA conducts monthly checks at the Omai operation and samples
the 38 wells at the mining site.
Checks are made for permeation of the wells and for the existence
of cyanide. Checks are also made for iron and copper content in the
water.
The samples are split between the company and the EPA so that the
results could be compared.
After the spill, a Commission of Enquiry was established to conduct
a probe into the incident and make recommendations. Three
committees were appointed to investigate various aspects of the
incident. They were the Environmental Audit and Socio-Economic
Assessment Committee, the Process Review Committee, and the Dam
Review Committee. The committees came up with recommendations
following investigations.
Fraser said the company had to comply with the recommendations for
it to be still in operation today. This was done and more, she
said.

